2023: In July, the internal audit of ISO 50001 was conducted at the Nueva Victoria and Coya Sur operations by the internal audit team and Roda. The Coya Sur plant achieved ISO 50001:2018 certification, valid from December 27, 2023, to December 26, 2026. See Certification here
2024: The first certification audit was carried out in Nueva Victoria (Mine & Leaching) obtaining the ISO 50001:2018 certification, valid from 2024-01-11 to 2027-01-10. See Certification here
2025: In January, an external follow-up audit for ISO 50001 was conducted at Nueva Victoria (Mine & Leaching) and Coya Sur, and the scope was expanded to include the Iodine Plant. Furthermore, the Nueva Victoria Plant is the first in the world to certify its production under the ISO 50001 standard. See Certification here